EPA Wants to Take More Than One Year to Decide on a Clean Air Act Permit? How Absurd!

The uncertain and often lengthy time to get permitting decisions is always near the top of the list of industry complaints. Section 165 of the Clean Air Act provides some relief by requiring certain permit decisions to be made within one year. Last week, in Avenal Power Center v. EPA, District Judge Richard Leon, in what may comfortably be described as a strongly-worded opinion, held that EPA may not circumvent the one-year limit on permit decisions by carving out from the one-year period the time spent by the Environmental Appeals Board reviewing EPA’s permit decision. 

In March 2008, Avenal Power filed an application for a PSD permit necessary to construct a new gas-fired power plant in the San Joaquin Valley in California. When EPA had not issued a decision within two years, Avenal sued. In February 2011, Gina McCarthy, head of EPA’s air office, announced that EPA would issue a permit decision by May 27, 2011. However, Judge Leon found EPA’s commitment to be “disingenuous,” because EPA's permit decision would be subject to EAB review, and EPA acknowledged that EAB review could take 6-18 months.

Judge Leon’s analysis was, in keeping with the statutory language, quite simple. Section 165 requires permit decisions within one year. EPA’s decision to provide appeals of permits to the EAB is a creature of regulation, not statute. The notion that EPA’s regulatory process could trump the statutory requirements is, to Judge Leon, “absurd.”

It is axiomatic that an act of Congress that is patently clear and unambiguous - such as this requirement in the CAA - cannot be overridden by a regulatory process created for the convenience of an Administrator, no matter how much notice and comment preceded its creation. "The rulemaking power granted to an administrative agency charged with the administration of a federal statute is not the power to make law. Rather it is the power to adopt regulations to carry into effect the will of Congress as expressed by the statute."

EPA apparently tried to persuade the court that section 165 is sufficiently ambiguous to give EPA discretion regarding whether it must squeeze the EAB process into the one-year time frame. Judge Leon’s response to what he called EPA’s “self-serving misinterpretation of Congress’s mandate”?

"Horsefeathers!"

One parochial note for my Massachusetts readers: Massachusetts DEP has recently announced that its permits – although labeled as “Final” – are not final until DEP's own internal adjudicatory hearing process has been completed. Massachusetts law has nothing comparable to Section 165 of the CAA, so MassDEP’s interpretation adds the insult of delay inherent in adjudicatory proceedings to the injury caused by the length of the normal permit process..

Is CO2 "Subject to Regulation" under the Clean Air Act? Time Will Tell (We Think).

In Massachusetts v. EPA, the Supreme Court concluded that greenhouse gases, including CO2, are “air pollutants,” the it left (barely) open the question whether CO2 is “subject to regulation” under the Clean Air Act (“CAA”). 

Following Massachusetts v. EPA, there have been a number of cases in which advocates of climate change regulation have sought to require EPA to regulate CO2 as a pollutant. One of those cases, In re Deseret Power Electric Cooperative, was just decided by the EPA Environmental Appeals Board. In Deseret Power, the Sierra Club had challenged issuance of a PSD permit issued by EPA Region 8 which would have allowed Deseret Power to construct a coal-fired power plant near Bonanza Utah. The basis for the challenge was the failure of EPA to impose a best available control technology, or BACT, limit on CO2 emissions.

Notwithstanding the decision in Massachusetts v. EPA, EPA took the position that it historically had not interpreted the term “subject to regulation under the Act” to include CO2. Moreover, it claimed in Deseret Power that it did not have authority to impose a BACT limit on CO2 emissions. The EAB firmly rejected EPA’s position that it did not have authority to impose BACT limits on CO2. However, the EAB also rejected the Sierra Club’s argument that EPA was required to impose compliance with BACT for CO2.  In fact, the EAB concluded that “the statute is not so clear and unequivocal as to preclude Agency interpretation of the phrase ‘subject to regulation under this act,’ and therefore the statute does not dictate whether the Agency must impose a BACT limit for CO2.”

So where does the Deseret Power decision leave the regulation of CO2 under the CAA?  Probably pretty much where it was before the decision was issued – that is, right in the lap of the new administration. However, if I were a betting man, I would certainly be reluctant to back new ventures that involve significant CO2 emissions unless the developer has a plan for addressing CO2 emissions.