CERCLA’s Three Year Statute of Limitations for Contribution Applies To Non-CERCLA Settlements

Parties which settle environmental liability in a judicially approved settlement have three years from the date of that settlement in which to seek contribution even if the settlement is not a CERCLA settlement.  That is the holding in a recent federal case in Montana, ASARCO LLC v. Atlantic Richfield Company.  There, ASARCO had entered into a 1998 consent decree under RCRA and the Clean Water Act to remediate a contaminated site that for over a century had been used as a lead smelting facility. … More

EPA Refuses to Amend Its Backup Generator Rule: Demand Response Breathes Easier

Last Friday, EPA published notice that it would not be revising its regulations on backup generators in response to three petitions for reconsideration it had received after it promulgated its final rule in January 2013. The rule had sparked controversy, because EPA allowed backup generators to operate for up to 100 hours a year, though EPA did require use of ultra-low sulfur diesel fuel beginning in January 2015.… More

You Can’t Estop the Government — Even When It Wants to Be Estopped

Last week, the 9th Circuit Court of Appeals issued a decision that arguably explains everything from why the Tea Party exists to why otherwise calm and sane executives suddenly lose all their hair. Perhaps most astounding, the decision is clearly correct. Perhaps the law is an ass.

In 2008, Avenal Power submitted an application to EPA for a PSD permit to construct a new 600 MW natural gas-fired power plant in Avenal,… More

Importance of Judicial Approval of CERCLA Settlements

Before a Superfund settlement becomes enforceable, it must be reviewed by a federal court to confirm that it is fair, reasonable, and consistent with CERCLA’s objectives.  This judicial review is at the heart of CERCLA’s settlement process.  Since Superfund settlements provide broad protection to settling parties, judicial approval provides the necessary and exclusive procedural mechanism  to vouchsafe that a proposed settlement is in the interest of the public as well as all  other parties.… More

How Much Deference Do States Get in Entering CERCLA Consent Decrees? Probably A Lot, But Perhaps Not As Much as You Thought

In Cannons Engineering, the First Circuit Court of Appeals famously stated that, when CERCLA consent decrees arrive at the courts of appeal for review, they do so “encased in a double layer of swaddling,” because both the EPA decision to enter into the decree and the district court review of the EPA decision are entitled to significant deference. Last week, in Arizona v.… More

The SJC Gives “Great Deference” to the Energy Facilities Siting Board. That’s An Understatement

In two related decisions last week, the Supreme Judicial Court issued three important rulings, and handed the Brockton Power Company one major problem in its long-running effort to build a combined-cycle gas plant in Brockton.

First, in City of Brockton v. EFSB, the SJC rejected all of the challenges by the City of Brockton and certain citizens to the Energy Facilities Siting Board approval of the Brockton Power project.… More